Data center restrictions face legal challenges

New limits on data center building face court challenges over local authority and zoning, as towns and states weigh pauses against demand for power and water.

by Trends DeskNovember 19, 20264 min read

Data center restrictions face legal challenges

New limits on data center building face court challenges across the United States, as towns and states weigh pauses on the projects against demand for power, water and land. The legal issues around data center restrictions often fall into three groups: environmental review, moratoria and land use.

Demand for data centers has grown with artificial intelligence, cloud computing and other digital services, and the scale of the buildings has brought complaints about water use, electricity demand and noise. Some local governments have adopted moratoria to study infrastructure capacity, update zoning rules and set standards before they review applications.

Moratoria have been challenged on grounds of limited local authority, due process, regulatory takings and vested rights, and developers may also challenge data center restrictions as arbitrary or aimed at one project.

Data center restrictions tested in Texas

Data center restrictions carry risk when a town acts without clear authority, as Hill County, Texas, showed in 2026. After the county adopted a one-year pause on new data-center construction in unincorporated areas, a developer sued, alleging that the county lacked authority and that the measure was a regulatory taking. The county later rescinded the moratorium and adopted a new checklist for developers, and as of July 2026 it was unclear whether the developers planned to keep litigating.

Other challenges to data center moratoria have come from developers whose applications were already pending. In Gibraltar, Michigan, developers challenged a one-year moratorium that they said wrongly reached an application submitted before the pause. Courts have also heard claims that bans were arbitrary, including challenges in Andover, Montgomery and Monroe in New Jersey.

Environmental review is a second front for data center restrictions. Projects with a federal link go through review under the National Environmental Policy Act, while state laws impose their own review, and the review is meant to test whether a project may cause a significant environmental effect. Water supply, energy demand, air quality and effects on nearby communities all come into the review, and a court can void a decision when the review is skipped or incomplete.

Litigation is already testing data center restrictions. In Pearson v. Amazon Data Services, Inc., filed in Oregon in March 2026, plaintiffs allege that wastewater from data-center and other operations adds to nitrate pollution in groundwater in the Lower Umatilla Basin. In NAACP v. X.AI Corp., plaintiffs allege that turbines at the Colossus 2 data center in Southaven, Mississippi, ran without a required air permit, and the Justice Department moved in June 2026 to intervene and dismiss the case.

Data center restrictions reach state capitols

New York's Senate and Assembly passed the Responsible Data Center Development Act on June 4, 2026, placing a one-year moratorium on permits for data centers expected to draw more than 20 megawatts. Governor Kathy Hochul did not sign it and instead signed Executive Order No. 62 on July 14, 2026, imposing a one-year moratorium on discretionary environmental permitting for data centers expected to draw more than 50 megawatts.

Senator Bernie Sanders introduced the Artificial Intelligence Data Center Moratorium Act on March 25, 2026, while S. 4214 and H.R. 9442 would impose a moratorium on data center development or upgrades. Fifteen states have bills pending to impose moratoria, according to the National Conference of State Legislatures, and Maine's governor vetoed one.

Zoning is the third front for data center restrictions, because many local land-use rules were not written with data centers in mind. A data center often does not fit neatly into existing classifications, and how it is classified can decide whether it is permitted outright, allowed conditionally, prohibited or subject to a zone change. In Prince William County, Virginia, neighboring landowners challenged a plan amendment that allowed data-center development, citing noise, light and visual effects, lower property values and stormwater pollution.

Not every locality is turning to data center moratoria. The Lumberton City Council in North Carolina voted unanimously on November 9, 2026, to approve rules limiting data centers to an industrial park, with a noise cap of 65 decibels, water-efficient cooling and annual energy reports. A developer has already approached the city about a data center using 50 megawatts of power and 50,000 gallons of water a day.

No single approach to data center restrictions removes the legal risk. Approvals, denials, moratoria and restrictive rules can all invite challenge, and the strongest approach rests on clear legal authority, a full record and standards that can be enforced.