GRAP construction delays hit Delhi-NCR housing projects

A Stage III pollution ban halted building across Delhi-NCR, and more than 400 housing projects with 1,98,000 homes face delays of three to four months.

by Trends DeskNovember 19, 20263 min read

GRAP construction delays hit Delhi-NCR housing projects

GRAP construction delays have hit housing projects across Delhi-NCR after the Commission for Air Quality Management invoked Stage III of the Graded Response Action Plan on 6 November. The ban halted building and demolition work, including excavation, piling, brickwork and highway building. The curbs were revoked on the night of 17 November as air quality improved, but developers say the stoppage will push back deliveries by months.

GRAP construction delays reach more than 400 projects

More than 400 under-construction residential projects, with over 1,98,000 housing units, were affected by the ban, according to data from property consultancy Anarock. Santhosh Kumar, vice-chairman of Anarock, said the bigger concern was the knock-on effect on project timelines, with a one-month building ban likely to delay projects by at least three to four months. Builders may face extra costs of as much as Rs 40 per sq ft because of the delays, Kumar said, with the exact figure depending on a project's scale, stage of building and the developer's capacity.

The Commission for Air Quality Management had already restricted dust-generating demolition and outdoor construction across Delhi-NCR from 5 to 20 November, in an order dated 30 October. Railways, metro, airports, inter-state bus terminals, hospitals, water and sanitation, defence and projects of national importance were exempt. The Delhi government separately bars dust-generating construction in the city from 1 November to 31 January under its winter action plan. The order is one of several that shape GRAP construction delays each winter.

GRAP construction delays grow as workers leave sites

A short ban rarely stays short on site. When work stops, migrant labourers move to other places, and contractors must reassemble their workforce once the curbs lift. Santhosh Kumar said even a short shutdown can stretch into longer delays as workers leave and contractors rebuild their teams. Labour is the main reason GRAP construction delays outlast the ban. Industry bodies have said it can take three to four days for work to restart in earnest once restrictions lift, and longer in some cases.

DLF Managing Director Ashok Tyagi said on the firm's earnings call last month that air quality levels were being watched closely, as GRAP restrictions sometimes stay in force for 30 to 40 days. That can pose a problem for building activity in the quarter ending December. The GRAP construction delays feed into quarterly results for listed developers with heavy NCR exposure. The Commission for Air Quality Management invoked Stage III on 6 November after Delhi's average air quality index reached about 382, and the city's AQI had risen from 117 on 31 October to 397 on 4 November.

GRAP construction delays add costs for buyers and builders

Developers say overheads do not pause when a site stops. Interest, salaries and equipment costs continue, while the buyer's delivery date stays the same. Anant Raj chief executive Aman Sarin said emission curbs on commercial vehicles can add three to four days to material transit at building sites, and that over a month this can raise logistics time and costs by 15 to 20 per cent. Sarin estimated that restrictions can shrink site workforces by 40 to 50 per cent as daily-wage workers leave in search of work. GRAP construction delays also raise financing costs, as revenue recognition slips with each week of halted work.

The Supreme Court has directed NCR states to compensate construction workers hit by GRAP shutdowns, with funds drawn from the labour cess collected on building projects. Delhi has announced Rs 10,000 per affected worker in the past. The curbs were lifted on 17 November, and the commission has said they could be reimposed if air quality worsens. GRAP construction delays will return in Delhi-NCR if the curbs come back.